Simulation Studies and Modelling Requirements

Simulation studies are crucial for design and operation of the power system.

Importance of Simulation Models

Simulation models are important for assessing the impacts of the installations on the network. 

Customers are required to:

  • Develop accurate models of their facilities
  • Conduct simulation studies using the models
  • Submit their self-assessment studies to EirGrid

General Requirements

A revision of this document is currently under development. For PQ, FRT and WECC related information, refer to the section below.

Requirements for Power Quality Studies

The EirGrid Policy on Harmonics - Issue No. 2, Revision No. 1, December 2013 given at the end of this document has been updated with this new policy:

Customers Required to Submit PQ Study

Customer type
Detail

TSO Generation

All customers

TSO Demand

All customers

PQ Study Submission Requirements

Item
Detail
Timeline

Customer Self-Assessment PQ Report

As described in our PQ Study Requirements document

At least 12 months before energisation

Requirements for Fault Ride-Through (FRT) Studies

Customers Required to Submit FRT Study

We don't require FRT study and WECC model submission from DSO customers < 5MW for connection point < 110 kV.

Customer type
Detail

TSO Generation

All customers

TSO Demand

For connection point ≥ 110 kV: All customers For connection point < 110 kV: Registered capacity ≥ 5 MW

FRT Study Submission Requirements

All items listed here should be submitted together, at least 12 months before energisation.

Item
Detail

Customer Self-Assessment FRT Report

As described in our FRT Study Template

Detailed SLD of the Facility

Must be legible

Facility FRT Dynamic Modelling Files

Detailed dynamic model with vendor-specific libraries (.raw, .seq, .sav, .dyr, .dll and .sld)

Validation Report for the FRT Dynamic Model

Factory or type tests to validate the responses of the dynamic model developed for the FRT analysis

Documents Used as Reference

For EirGrid’s records

Requirements for WECC Models

Customers Required to Submit WECC Models

We don't require FRT study and WECC model submission from DSO customers < 5MW for connection point < 110 kV.

Customer type
Detail

TSO Generation

All customers

TSO Demand

For connection point ≥ 110 kV: All customers For connection point < 110 kV: Registered capacity ≥ 5 MW

WECC Study Submission Requirements

Item
Detail
Timeline

Submission of WECC Model Parameters

Use our spreadsheet for WECC model parameters submission

At least 3 months before energisation

Validation Report for the Provided WECC Model Parameters

As described in our Requirements for WECC Model Submission document

No later than 6 weeks after the completion of Grid Code Compliance Tests, including approval of the test reports by EirGrid